Sample contractor payment plan

You do not pay the contractor in advance, but in instalments linked to the construction phases. You pay each instalment only once the supervising engineer has certified that the phase has actually been completed. This is an example for a house, a villa or a residential building; the percentages are adjusted to the contract and the design.

Example instalment schedule

PhaseCondition for paymentShare
Advance paymentContract signed, bank guarantee for repayment of the advance10%
Foundations and below-ground worksSupervision has approved the reinforcement before concreting and the completed foundations15%
Load-bearing structureSlabs, walls and columns completed, certified by supervision25%
Roof and waterproofingRoof closed, waterproofing completed, certified by supervision15%
Building services, windows and doors, façadeBuilding services inspected before the walls are closed, certified by supervision15%
Finishing worksWorks completed, list of defects drawn up15%
RetentionDefects corrected after handover and the technical inspection5%

Rules that apply to every instalment

How construction is contracted and what to look for in a bid is explained on the pages How construction is contracted and Contractor bid check.

Note: this is an example, not legal advice. The actual payment plan depends on the contract, the type of construction and the agreement with the contractor.