How long it takes

Indicative durations of each phase from our experience, from the first study to the use permit (uporabna dozvola). This is a guide for planning, not a promise of a deadline: the permit depends on the office handling it, and construction on the building and on what changes along the way.

Phases and durations

  1. Study and first conceptup to a month
  2. Main design (glavni projekt)about two months
  3. Building permit (građevinska dozvola)several months, depending on the office handling the procedure
  4. Building a small residential building, up to 6 apartmentsabout a year, without fit-out
  5. Building a 250 m² houseabout a year and a half, with fit-out
  6. Technical inspection and use permitup to two months after all works are complete

The length of each bar is proportional to the duration. A dashed bar means the duration does not depend on us.

What most often extends the work

For your building we prepare an indicative programme before the first spade goes in, as part of the design.